Day 169 of the build

We're building a lunch kitchen in Makola.

Rice and curry cooked every morning, at your workplace gate by 12:15. Opening early 2027. Join the early list and we'll call you before the first day.

  1. Land
  2. Foundations
  3. Floor
  4. Walls
  5. Roof next
  6. Fit‑out
  7. Open
The kitchen's block walls finished, with scaffolding ready for the roofDay 156 · 6 Oct 2026
Walls done. Roof next.Our site, Makola
The plot as coconut land before clearing
Day 1
A JCB levelling the plot
Day 5
The hand-drawn kitchen plan on squared paper
Day 31
Laying the foundation stone
Day 32
Ground beam steel along the foundations
Day 68
Levelling the floor slab under floodlights at night
Day 106
A mason laying blocks after dark
Day 128
The block walls at full height
Day 144
Block walls with a window frame fitted
Day 150